
Trent Valley – Shardlow & Willington
Site:
Trent Valley – Shardlow & Willington
Date:
November 2020 - February 2021
Value:
The Rothen Group were asked by Canal & River Trust and Kier to assist with ‘Transforming the Trent Valley Towpath Project’ at Shardlow & Willington. The towpath needed improving and upgrading with soft bank protection and timber sleeper retaining walls required too. The works were over 2.75km within a Conservation & Heritage Area.

The Project
On site meetings to establish best plant/equipment and methodology for undertaking works in conservation & heritage areas in a sensitive manner
Versatile kit to get plant & materials to site where access was very awkward
Managing boat & towpath users during the works
Clearing the old towpath
Difficulties in getting materials to site
Laying new towpath to different specifications in different areas
Installing edging boards and blending towpath in other places
Finishing site with topsoil & seed
Experienced team with heritage training
Bank protection works
Through having a wide range of floating plant the difficult access was easily overcome. We used a 2.5t marine ready excavator for scarifying and clearing the old towpath. As much of the existing topsoil was blended into the verge to save taking material off site. After laying edge boards where needed and membrane, the grab barge was used to offload Type 1 sub base and then the Centrac top coat directly onto the towpath.
The towpath was widened for over 100m section where the existing bank had collapsed and a timber sleeper retaining wall was installed. In addition soft bank protection measures of coir rolls & hazel faggots were installed along another collapsed bank section.
The towpath was widened for over 100m section where the existing bank had collapsed and a timber sleeper retaining wall was installed. In addition soft bank protection measures of coir rolls & hazel faggots were installed along another collapsed bank section.
Our floating grab barge was able to transport some materials to site and self offload directly onto the towpath with a clamshell. We loaded the materials at our wharf and floated them to site using pusher tugs and hoppers. This kept cost down as larger loose tip orders of materials could be made rather despite the difficult access on site. The grab barge could unload from either its own hold tank or the hoppers tank and ensure a steady stream of material for the team working to level and compact the towpath.
A centrac top coat was applied and then topsoil brought in where necessary and blended in with grass seed to finish. These works were undertaken with minimal supervision and to a high standard, in conjunction with our pragmatic approach to these type of projects.

FEATURED CASE STUDY
Habitat Creation Coney Meadows, Droitwich
Coney Meadows is part of a nationwide project to restore the UK’s wetlands. Since the 17th century, large areas of reedbeds have been stripped and converted into agricultural land, massively reducing the number of habitats available for wetland animals.

FEATURED CASE STUDY
Changing the Shape of the River Derwent, Derby
Following the storm seasons of 2023 & 2024, the EA set out to review its impact on the UK’s waterways. The River Derwent in Derby was flagged after a sonar scan of its navigation identified a scour hole – a direct result of heavy rainfall pushing sediment downstream.
Our Accreditations








